Valverde OSP Project Area
Click for larger view
Valverde OSP Project Schedule
NOTICE TO PROCEED – 11-2-22
BASELINE HYDROLOGY – 16 weeks – Fri 11/18/22 – Thu 3/9/23
ALTERNATIVES ANALYSIS – 20 weeks – Thu 3/9/23 – Thu 7/27/23
CONCEPTUAL DESIGN – 14 weeks Thu 7/27/23 Thu 11/2/23
PROJECT COMPLETION – 11/2/23
Valverde OSP Project Team Meetings
Valverde OSP Project Kickoff Meeting Minutes
November 28, 2022
Valverde OSP Progress Meeting Minutes
January 4, 2023